What is Underground Surveying?
Underground surveying embraces the survey operations performed beneath the surface of the earth in connection with tunneling, exploration and construction in subterranean passageways. It is quite different from surveying on the surface. The following peculiarities of underground surveys indicate how they differ from surface surveys:- Artificial illumination is required to view instrument crosshairs, to read verniers, to sight targets etc. Because of poor lighting.
- Working space in passageways is often cramped.
- Instrument stations and benchmarks for levelling must often be set into the roof of a passageway to minimize disturbance from the operations being carried on in the workings.
- Instrument stations are set with some difficulty since plugs must be driven into drill holes in rock.
- In many instances the underground workings arc wet, with considerable water dripping from the roofs of passage ways and running along the floors.
Applications of Underground Surveys
The major application of underground surveys is in the construction of tunnels and other underground utilities. The tunnel is constructed when open excavation becomes uneconomical usually when it is more than 20 m. It- Reduces the grade
- Shortens the distance between given points separated by a dividing mountain or ridge.
- Meets the demand of-modern rapid transit in a city.
- Engineering operations to be performed
- Exact alignment
- Proper gradient
- Establishment of permanent stations marking the proposed route.
The survey work in connection with tunneling can be divided into:
- Surface survey
- Transferring the alignment underground
- Levels in tunnels
Surface survey:
Surface survey connects points representing each portal of a tunnel. A traverse connecting the portal points determines the azimuth, distance and differences in elevation of each end of the proposed tunnel. Based on the local conditions and proposed length of the tunnel the methods of working are adopted. It is always advisable that the survey is based on the suitable local coordinate system. The alignment is permanently referenced by a system of monuments within an area outside each tunnel portal. And here is sketch regarding how the tunneling work proceeds. Central line and grade stakes within the tunnel are usually set in the roof to avoid displacement and destruction by the constant flow of people and machinery as construction proceeds. If the stakes are set on the floor they should be offset into an area along the tunnel's edge.Transferring the alignment underground
For long tunnel excavation is carried inward from both parties. But vertical shafts are also sunk up to the required depth along the alignment of the tunnel at intermediate locations along the routes. The vertical alignment can be done by- Plumb bob
- Optical collimator
- Laser
- More convenient than a plumb bob.
- Can be used to set marks directly on the floor of a completed shaft
- No wires as in case of plumb bob.
Levels in tunnels:
In transferring levels underground, little difficulty is encountered at the ends of the tunnel, but at the shaft use is made of- Steel tape
- Chain
- Constructed rods
- Steel wires
Figure showing how the depth is measured by steel tape
Figure showing Depth measured by EDM
The important features of EDM are:- EDMI unit and reflectors should be in the same vertical line.
- Both are mounted on stable support.
- Visibility should be good for EDMI to operate.