🕑 Reading time: 1 minute
Waterproofing of toilets is required to prevent seepage of water from floor slab and walls as toilet involves use of water and has plumbing works.Contents:
Casting of Slab and Plumbing Works in Toilets
Casting of Slab and Plumbing Works in toilets are done in following ways: 1. Either the toilet slab is casted a foot below the outside slab, then plumbing pipes are laid as designed, then cover the pipes with filler materials, followed by tiling on top 2. Toilet slab is casted the same level of outer slab, then holes made in slab and piping is laid at bottom of slab visible from lower floor which is later covered by false ceiling. Benefit of this type is ease for the maintenance, anytime false ceiling can be opened in case of leakage and plumbing can be repairedMethod of Waterproofing of Toilets
The old method of waterproofing was make a layer cement plaster added with chemical. Modern methods employ waterproofing membranes in this area too. Generally there are two types of waterproofing membranes:- Sheet membrane
- Liquid membrane
Required tools and materials for Waterproofing of Toilets
Brush, scrapper, paint brush, roller tray, caulking gun Primer, tape & silicon, waterproofing membraneSurface preparation
Surface to be free of all dust, loose particles, no contaminants, should be scrapped to make it smooth, walls should be brushed to remove the undulations.Priming of Toilet Surfaces
Primer is applied with help of roller brush up to required height of the wall and then on the floor.Bond Breakers
When the primer goes dry we will use combination of silicon and tape. Tape to be applied on four walls at required height. This is to ensure that waterproofing is done up to this height only. Sometimes waterproofing is required to complete height of the toilet walls or sometimes may be 1-foot height only as per the requirement. Silicon is then put in all the corners vertically and horizontally very carefully to ensure no gap is left.First Coat of Waterproofing for Toilets
Start applying the membrane with a paint brush starting from the corners where silicon is applied make sure we pay extra attention to make 100 % coverage as this is the most critical area.


Second Coat of Toilet Waterproofing
After the first coat dries, put the second coat similar as above, carefully brush on the corners and joints and roller on the walls and floor, we can use a different color to make sure no area is left of waterproof coat.