Methods of preparation of preliminary or approximate construction cost estimation for studies of various aspects of work of project and its administrative approval is discussed. This estimate can decide, in case of commercial projects, whether the net income earned justifies the amount invested or not. The approximate estimate is prepared from the practical knowledge and cost of similar works. The estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or layout plan. A percentage 5 to 10% is allowed for contingencies.Contents:
Methods of Approximate Construction Cost Estimation Preparation
The following are the methods used for preparation of approximate construction cost estimates:- Plinth area method
- Cubical contents method
- Unit base method
a) Plinth area method:
The cost of construction is determined by multiplying plinth area with plinth area rate. The area is obtained by multiplying length and breadth (outer dimensions of building). In fixing the plinth area rate, careful observation and necessary enquiries are made in respect of quality and quantity aspect of materials and labour, type of foundation, height of building, roof, wood work, fixtures, number of storeys etc. As per IS 3861-1966, the following areas include while calculating the plinth area of building:Types of Estimates:
- Area of walls at floor level.
- Internal shafts of sanitary installations not exceeding 2.0 sqm, lifts, air-conditioning ducts etc.,
- Area of barsati at terrace level: Barsati means any covered space open on one side, constructed on one side, constructed on terraced roof which is used as shelter during rainy season.
- Porches of non-cantilever type.
Areas which are not to include
- Area of lofts.
- Unenclosed balconies.
- Architectural bands, cornices etc.,
- Domes, towers projecting above terrace level.