In construction Project, What is the meaning of the term Float?
Crazing often occur within a few hours of plaster being applied to the wall and cracks may hardly be visible until dust or moisture makes them noticeable. These cracks normally occurs when a plaster mix with a high cement content is used or the plaster is allowed to dry too quickly.
Crazing often occur within a few hours of plaster being applied to the wall and cracks may hardly be visible until dust or moisture makes them noticeable. These cracks normally occurs when a plaster mix with a high cement content is used or the plaster is allowed to dry too quickly.
See less
nikeetasharma
In construction project, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: 1.subsequent tasks ("free float"). 2.project completion date ("total float").
In construction project, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:
1.subsequent tasks (“free float”).
See less2.project completion date (“total float”).