Quantity of materials such as cement, sand, coarse aggregates and water required per cubic meter of concrete and mortar for different mix proportions varies with the mix design of the concrete and mortar respectively. Following table gives the estimated quantity of materials required per cubic meter of mortar and concrete for various nominal mixes.Quantities of Materials Per Cubic Meter of Concrete Mix Proportions
Nominal Mix | Water Cement Ratio | Water per 50Kg Bag of Cement | Cement | Sand (CUM) | Crushed Stones (CUM) | |||
Cement | F.A. | C.A. | By Weight (Kg) | By Number of Bags | ||||
1 | 1 | - | 0.25 | 12.5 | 1015 | 20.3 | 0.710 | - |
1 | 1.5 | - | 0.28 | 14 | 815 | 16.3 | 0.855 | - |
1 | 2 | - | 0.3 | 15 | 687 | 13.74 | 0.963 | - |
1 | 2.5 | - | 0.35 | 17.5 | 585 | 11.7 | 1.023 | - |
1 | 3 | - | 0.4 | 20 | 505 | 10.1 | 1.06 | - |
1 | 4 | - | 0.53 | 26.5 | 395 | 7.9 | 1.106 | - |
1 | 6 | - | 0.7 | 35 | 285 | 5.7 | 1.197 | - |
1 | 8 | - | 0.9 | 45 | 220 | 4.4 | 1.232 | - |
1 | 1 | 2 | 0.3 | 15 | 560 | 11.2 | 0.392 | 0.784 |
1 | 2 | 2 | 0.42 | 21 | 430 | 8.6 | 0.602 | 0.602 |
1 | 1.5 | 3 | 0.42 | 21 | 395 | 7.9 | 0.414 | 0.828 |
1 | 1.66 | 3.33 | 0.48 | 24 | 363 | 7.26 | 0.419 | 0.838 |
1 | 2 | 3 | 0.5 | 25 | 385 | 7.7 | 0.539 | 0.808 |
1 | 2 | 3.5 | 0.53 | 26.5 | 330 | 6.6 | 0.462 | 0.808 |
1 | 2 | 4 | 0.55 | 27.5 | 310 | 6.2 | 0.434 | 0.868 |
1 | 2.5 | 3.5 | 0.57 | 28.5 | 305 | 6.1 | 0.534 | 0.748 |
1 | 2.5 | 4 | 0.6 | 30 | 285 | 5.7 | 0.499 | 0.798 |
1 | 3 | 4 | 0.65 | 32.5 | 265 | 5.3 | 0.556 | 0.742 |
1 | 2.5 | 5 | 0.65 | 32.5 | 255 | 5.1 | 0.446 | 0.892 |
1 | 3 | 5 | 0.69 | 34.5 | 240 | 4.8 | 0.504 | 0.84 |
1 | 3 | 6 | 0.75 | 37.5 | 215 | 4.3 | 0.452 | 0.904 |
1 | 4 | 8 | 0.95 | 47.5 | 165 | 3.3 | 0.462 | 0.924 |