Join

Join TheConstructor to ask questions, answer questions, write articles, and connect with other people. When you join you get additional benefits.

Have an account? Log in
Continue with Facebook
Continue with Google
or use


Have an account? Log in Now

Log in

Log in to TheConstructor to ask questions, answer people’s questions, write articles & connect with other people. When you join you get additional benefits.

Join Here

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Log in Now

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here
Become VIP Member

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here
Become VIP Member
The Constructor Logo The Constructor Logo
Log inJoin

The Constructor

The Constructor Navigation

  • Articles
    • Recent Articles
    • Popular Articles
    • Write Article
  • Questions
    • Recent Questions
    • Popular Questions
    • Polls
    • Ask a Question
  • Categories
    • How To Guide
      • Material Testing Guide
    • Concrete
    • Building
      • Brick Masonry
      • Building Materials
      • Building Tips
    • Construction
      • Equipments
      • Management
    • Digital tools
    • Geotechnical
      • Foundation
Search
VIP Dashboard

Mobile menu

Close
Ask a Question
  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Aswany Sreejith - Questions

Home/ Aswany Sreejith/Questions
Ask Aswany Sreejith

Do you need to remove the ads? Become VIP Member

  • About
  • Questions
  • Polls
  • Answers
  • Best Answers
  • Asked Questions
  • Followed Questions
  • Favorite Questions
  • Articles
  • Comments
  • Groups

Discy Latest Questions

Asked: July 7, 2020In: Structural Engineering

How to design Formwork?

Aswany Sreejith
Aswany Sreejith

Aswany Sreejith

  • 1 Question
  • 0 Answers
  • 0 Best Answers
  • 5 Points
View Profile
Aswany Sreejith User

What is the procedure of designing the formwork?

  1. nikeetasharma

    nikeetasharma

    • 23 Questions
    • 303 Answers
    • 0 Best Answers
    • 2,680 Points
    View Profile
    nikeetasharma Guru
    Added an answer on October 15, 2020 at 4:25 pm

    Formwork is the term used for the process of creating a temporary mould into which concrete is poured and formed. Traditional formwork is fabricated using timber, but it can also be constructed from steel, glass fibre reinforced plastics and other materials. There are three types of formwork :- -BeaRead more

    Formwork is the term used for the process of creating a temporary mould into which concrete is poured and formed. Traditional formwork is fabricated using timber, but it can also be constructed from steel, glass fibre reinforced plastics and other materials.

    There are three types of formwork :-

    -Beam formwork :-
    Formwork for beams takes the form of a three-sided box which is supported and propped in the correct position and to the desired level. The removal time for the formwork will vary with air temperature, humidity and consequent curing rate. Typical striking times are as follows (using air temperature of 7-16 ºC):

    i) Beam sides: 9-12 hours.
    ii) Beam soffits: 8-14 days.
    iii) Beam props: 15-21 days.

    -Column formwork :-
    This consists of a vertical mould of the desired shape and size of the column to be poured. As a means of keeping the formwork material thickness to a minimum, horizontal steel or timber clamps (or yokes) are used at equal centres for batch filling and at varying centres for filling that is completed in one pour.

    The head of the column formwork can be used to provide support for the beam formwork, but while this gives good top lateral restraint it can make the formwork complex. Alternatively, the column can be cast to the underside of the beams. Later on, a collar of formwork can be clamped around the cast column to complete the casting and support the incoming beam formwork.

    -Plastic formwork :-
    Re-usable plastic formwork is generally used for quick pours of concrete. The formwork is assembled either from interlocking panels or from a modular system and is used for relatively simple concrete structures. It is not as versatile as timber formwork due to the prefabrication requirements and is best suited for lost-cost, repetitive structures such as mass housing schemes.

    Stay-in-place structural formwork is generally assembled on site using prefabricated fibre-reinforced plastic. It is used for concrete columns and piers and stays in place, acting as permanent axial and shear reinforcement for the structural member. It also provides resistance to environmental damage for both the concrete and reinforcing bars.

    Proprietary systems are used to support vertical formwork while concrete cures, consisting of a series of tubes and ties.

    See less
    • 27
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  • 0
  • 4 4 Answers
  • 206 Views
  • 0 Followers

Sidebar

Popular Articles

  • Gopal Mishra

    Types of Foundation for Buildings and their Uses [PDF]

  • Gopal Mishra

    Compressive Strength of Concrete -Cube Test [PDF], Procedure, Results

  • Padmanabhan G

    Methods of Rainwater Harvesting [PDF]: Components, Transport, and Storage

  • Sadanandam Anupoju

    16 Types of Heavy Equipment Used in Construction

  • Fasi Ur Rahman

    Standard Size of Rooms in Residential Building and their Locations

Recent Articles

  • Xian

    Bricklaying Robots in Construction #2

  • Xian

    Welcome to the Gutenberg Editor

  • Xian

    Bricklaying Robots in Construction

  • Ravi Panwar

    Rongjiang Bridge: The World’s Longest Bridge of Rigid Girder and Flexible Arch

  • Ravi Panwar

    Qinghai–Tibet Railway: The Longest and Highest Highland Railway in the World

Recent Questions

  • Shailendra

    In what case is a Shear Key provided in Foundation?

    • 0 Answers
  • Salman

    What is piping technology for termite treatment in building?

    • 0 Answers
  • nikeetasharma

    Which instrument is widely used for surveying?

    • 1 Answer
  • nikeetasharma

    Which type of reinforcement are used in pre-stressing?

    • 0 Answers
  • Bhavani Pesaru

    How can we use magnetic levitation method in civil engineering?

    • 0 Answers

Explore

  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Footer

  • Home
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
  • Ask Questions
  • Write for us
  • Popular Questions
  • Facebook
  • Instagram
  • Telegram

© 2009-2021 The Constructor. All Rights Reserved.