Analysis of rates for building works is the process of separation of works into components/elements (Viz. Labour, materials, machinery,transport, overheads and profit) of work and pricing them.Contents:
Analysis of rates is required for:
- Insertion in a tender (i.e.) as a lump sum, item rates
- To check reasonability of rates inserted by tenderers
- To assess various quantities of labour, materials, machinery, money and to effect economy by using alternatives and to optimize the resources
- To assess the rates payable for deviations, extra items of work to the builder
- To compare the costs with sanctioned amount and to take action for regularization of excess/ less cost
- To workout the budget and cash flows at various stages of the work and arranging interim/ final payments
- To detect irrational rates quoted by tenderers
- To serve as basic data in case of disputes that may arise at a later stage