Is it possible to obtain some data on factors on which seepage in dams depends?
Hi devilart, This method is used to compute the vertical and horizontal stresses of any shape ,irregular geometry below any point outside or inside The chart as shown in the above figure essentially consists of n no. of radial lines and m no. of concentric circles. To find out vertical stressRead more
Hi devilart, This method is used to compute the vertical and horizontal stresses of any shape ,irregular geometry below any point outside or inside
The chart as shown in the above figure essentially consists of n no. of radial lines and m no. of concentric circles.
To find out vertical stress at any point below or outside the loaded area, Plan of the loaded area is drawn such that depth Z at which stress is being computed equals the length AB as shown on
Further, the plan is placed over influence chart such that the point below which stress is required coincides with the center of chart Then count the number of influence area (N) covered by the plan
See less
AdityaBhandakkar
Absolutely Yes, factors of seepage are very important to determine before the construction of a dam or even after the construction of the dam for maintenance work. Electrical resistivity method is used to determine the amount of seepage and depth of seepage. As a civil engineer, it's our responsibilRead more
Absolutely Yes, factors of seepage are very important to determine before the construction of a dam or even after the construction of the dam for maintenance work.
Electrical resistivity method is used to determine the amount of seepage and depth of seepage.
As a civil engineer, it’s our responsibility to provide higher safety.
Seepage under the embankment is very much dangerous as compared to concrete dams because embankments are built on a very soft material which is easily scoured and it is very vulnerable for the influence of water.
On other side concrete dam, is built on hard strata and even the defective dam which not the endangered by passing of water from the underside.
Following are the methods for controlling seepage