Join

Join TheConstructor to ask questions, answer questions, write articles, and connect with other people. When you join you get additional benefits.

Have an account? Log in
Continue with Facebook
Continue with Google
or use


Have an account? Log in Now

Log in

Log in to TheConstructor to ask questions, answer people’s questions, write articles & connect with other people. When you join you get additional benefits.

Join Here

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Log in Now

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here
Become VIP Member
The Constructor Logo The Constructor Logo
Log inJoin

The Constructor

The Constructor Navigation

  • Articles
    • Recent Articles
    • Popular Articles
    • Write Article
  • Questions
    • Recent Questions
    • Popular Questions
    • Polls
    • Ask a Question
  • Categories
    • How To Guide
      • Material Testing Guide
    • Concrete
    • Building
      • Brick Masonry
      • Building Materials
      • Building Tips
    • Construction
      • Equipments
      • Management
    • Digital tools
    • Geotechnical
      • Foundation
Search
VIP Dashboard

Mobile menu

Close
Ask a Question
  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

How to design Formwork?

Home/ Questions/Q 45527
Next
In Process

Do you need to remove the ads? Become VIP Member

Asked: July 7, 20202020-07-07T21:38:16+05:30 2020-07-07T21:38:16+05:30In: Structural Engineering
Aswany Sreejith
Aswany Sreejith

Aswany Sreejith

  • 1 Question
  • 0 Answers
  • 0 Best Answers
  • 5 Points
View Profile
Aswany Sreejith User

What is the procedure of designing the formwork?

  • 0
  • 4 4 Answers
  • 201 Views
  • 0 Followers
  • 0
  • Share
    Share
    • Share on Facebook
    • Share on Twitter
    • Share on LinkedIn
    • Share on WhatsApp

4 Answers

  • Voted
  • Oldest
  • Recent
  1. aviratdhodare

    aviratdhodare

    • 37 Questions
    • 252 Answers
    • 0 Best Answers
    • 480 Points
    View Profile
    aviratdhodare
    2020-08-02T08:59:00+05:30Added an answer on August 2, 2020 at 8:59 am

    Column Formwork

    Before erecting column formwork, make sure the steel is checked and ready for casting.

    1. Place the formwork for column from predetermined grids.
    2. Plumb it from both sides and support it securely using adjustable steel props.
    3. The angle of propping should be 45° to the floor.
    4. Make sure the props are secured properly to the column formwork and floor, adjustment for pulling and pushing is operational.
    5. Start the position of column clamps from a storey rod.
    6. Transfer the clamps position to formwork from rod.
    7. During wedging, use nails to support arms of column.
    8. Place and wedge the base, center and top clamp sets.
    9. Check the formwork, looks square or not from the top.
    10. Place and wedge the remaining of the column clamps.
    11. Place a plumb bob hanged from a gauge block, plumb the column.

    Make a final check for plumb if the formwork is safely propped and column alignment before and right after the concrete is poured and vibrated.

    Beam formwork
    1 Thicken timber of strengthening plywood must be provided to beams soffit.
    2. Beams side – 18 mm plywood, 25 mm boards, studs 500 to 600 mm centers.
    3. Walkers and ties over 600 mm must provide
    4. If possible, use angle fillets to soffit joints.
    5. For calls work allowance made for height adjustment.

    Constructing beam framework erections sequence is
    1.Mark sole plates position
    2. Setting heights of falsework
    3. Erect side walls and construct beam soffit.
    4. Take the proper position of the soleplate.

    Staircase Formwork

    Points to be considered

    • The formwork should support the concrete weight. The weight of the throat of both stair and step should be upheld.
    • Formwork should be tied very tightly together to hold the sideways movement because of the slope the force is transferred sideways.
    • Consider the finish of the stair treads and type of nosing.
      Space may have to be left for the purpose made nosing.
    • 32
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  2. AdityaBhandakkar

    AdityaBhandakkar

    • 11 Questions
    • 250 Answers
    • 2 Best Answers
    • 0 Points
    View Profile
    AdityaBhandakkar User
    2020-09-05T08:24:14+05:30Added an answer on September 5, 2020 at 8:24 am
    How to design Formwork?

    Hi,

    For the design of homework, virtually a basic understanding of how the Concrete behaves on a particular time. How much pressure it exerts on formwork is necessary.

    Following are some properties for the designing of formwork

    1. Rate of a pour of Concrete: during pouring of Concrete, the weight of Concrete is directly proportional to the rate, which is it pours by transit mixer.in this case, the two conditions will love the Concrete will start hardening during pouring, which leads to less pressure developed on formwork, but if the Concrete does not start hardening, then pressure develops greater on formwork.
    2. Weight of concrete poured:  pressure exerted on formwork is directly proportional to the weight of concrete.if the weight of concrete is less than the pressure exerted is also less.
    3. Height of framework required for Concrete: the height of Concrete is the most important aspect because height and weight are directly proportional to the pressure applied on formwork. If the height of the casting member is is more than pressure develops on homework is also large.
    4. Cement type used for concreting: type of cement is related to the rate of hardening of the cement. If Concrete harder and faster, which allows a faster poor rate.so that is site engineer at just the polling rate of Concrete.
    5. The method adopted for vibrating: there are two types of vibrating techniques used, internal and external vibration. If internal vibrating is used with the help of a vibrating needle, then concrete acts like a pure liquid. So pressure act on formwork is large. (ACI recommends if external vibration used then reduce 10% in pressure formula).
    6. Water to cement ratio of Concrete that is a slump of Concrete: if a slump value of Concrete is more than concrete acts like a liquid which exerts a large pressure on formwork.
    7. External admixtures or additives used: chemical admixtures effects on hardening time of concrete. Basically, it acts as a retiring agent or plasticizer. Which also affects on formwork design.
    • 42
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  3. AdityaBhandakkar

    AdityaBhandakkar

    • 11 Questions
    • 250 Answers
    • 2 Best Answers
    • 0 Points
    View Profile
    AdityaBhandakkar User
    2020-10-15T11:49:39+05:30Added an answer on October 15, 2020 at 11:49 am
    This answer was edited.

    Hi, For the design of formwork as per technical and legal specifications, please refer IS 456: 2000. These codes describe the detail of formwork and their applications. Thank you.

    • 34
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  4. nikeetasharma

    nikeetasharma

    • 23 Questions
    • 303 Answers
    • 0 Best Answers
    • 2,680 Points
    View Profile
    nikeetasharma Guru
    2020-10-15T16:25:00+05:30Added an answer on October 15, 2020 at 4:25 pm

    Formwork is the term used for the process of creating a temporary mould into which concrete is poured and formed. Traditional formwork is fabricated using timber, but it can also be constructed from steel, glass fibre reinforced plastics and other materials.

    There are three types of formwork :-

    -Beam formwork :-
    Formwork for beams takes the form of a three-sided box which is supported and propped in the correct position and to the desired level. The removal time for the formwork will vary with air temperature, humidity and consequent curing rate. Typical striking times are as follows (using air temperature of 7-16 ºC):

    i) Beam sides: 9-12 hours.
    ii) Beam soffits: 8-14 days.
    iii) Beam props: 15-21 days.

    -Column formwork :-
    This consists of a vertical mould of the desired shape and size of the column to be poured. As a means of keeping the formwork material thickness to a minimum, horizontal steel or timber clamps (or yokes) are used at equal centres for batch filling and at varying centres for filling that is completed in one pour.

    The head of the column formwork can be used to provide support for the beam formwork, but while this gives good top lateral restraint it can make the formwork complex. Alternatively, the column can be cast to the underside of the beams. Later on, a collar of formwork can be clamped around the cast column to complete the casting and support the incoming beam formwork.

    -Plastic formwork :-
    Re-usable plastic formwork is generally used for quick pours of concrete. The formwork is assembled either from interlocking panels or from a modular system and is used for relatively simple concrete structures. It is not as versatile as timber formwork due to the prefabrication requirements and is best suited for lost-cost, repetitive structures such as mass housing schemes.

    Stay-in-place structural formwork is generally assembled on site using prefabricated fibre-reinforced plastic. It is used for concrete columns and piers and stays in place, acting as permanent axial and shear reinforcement for the structural member. It also provides resistance to environmental damage for both the concrete and reinforcing bars.

    Proprietary systems are used to support vertical formwork while concrete cures, consisting of a series of tubes and ties.

    • 27
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp

You must login to add an answer.

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Need An Account, Join Here

Sidebar

Popular Articles

  • Gopal Mishra

    Types of Foundation for Buildings and their Uses [PDF]

  • Gopal Mishra

    Compressive Strength of Concrete -Cube Test [PDF], Procedure, Results

  • Padmanabhan G

    Methods of Rainwater Harvesting [PDF]: Components, Transport, and Storage

  • Sadanandam Anupoju

    16 Types of Heavy Equipment Used in Construction

  • Fasi Ur Rahman

    Standard Size of Rooms in Residential Building and their Locations

Recent Articles

  • Xian

    Bricklaying Robots in Construction #2

  • Xian

    Welcome to the Gutenberg Editor

  • Xian

    Bricklaying Robots in Construction

  • Ravi Panwar

    Rongjiang Bridge: The World’s Longest Bridge of Rigid Girder and Flexible Arch

  • Ravi Panwar

    Qinghai–Tibet Railway: The Longest and Highest Highland Railway in the World

Recent Questions

  • Shailendra

    In what case is a Shear Key provided in Foundation?

    • 0 Answers
  • Salman

    What is piping technology for termite treatment in building?

    • 0 Answers
  • nikeetasharma

    Which instrument is widely used for surveying?

    • 1 Answer
  • nikeetasharma

    Which type of reinforcement are used in pre-stressing?

    • 0 Answers
  • Bhavani Pesaru

    How can we use magnetic levitation method in civil engineering?

    • 0 Answers

Explore

  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Footer

  • Home
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
  • Ask Questions
  • Write for us
  • Popular Questions
  • Facebook
  • Instagram
  • Telegram

© 2009-2021 The Constructor. All Rights Reserved.