Join

Join TheConstructor to ask questions, answer questions, write articles, and connect with other people. When you join you get additional benefits.

Have an account? Log in
Continue with Facebook
Continue with Google
or use


Have an account? Log in Now

Log in

Log in to TheConstructor to ask questions, answer people’s questions, write articles & connect with other people. When you join you get additional benefits.

Join Here

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Log in Now

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here
Become VIP Member
The Constructor Logo The Constructor Logo
Log inJoin

The Constructor

The Constructor Navigation

  • Articles
    • Recent Articles
    • Popular Articles
    • Write Article
  • Questions
    • Recent Questions
    • Popular Questions
    • Polls
    • Ask a Question
  • Categories
    • How To Guide
      • Material Testing Guide
    • Concrete
    • Building
      • Brick Masonry
      • Building Materials
      • Building Tips
    • Construction
      • Equipments
      • Management
    • Digital tools
    • Geotechnical
      • Foundation
Search
VIP Dashboard

Mobile menu

Close
Ask a Question
  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Minimum time required to complete activities in residential building construction?

Home/ Questions/Q 20477
Next
In Process

Do you need to remove the ads? Become VIP Member

Asked: December 13, 20172017-12-13T18:03:24+05:30 2017-12-13T18:03:24+05:30In: Construction Site Related
Gopal Mishra
Gopal Mishra

Gopal Mishra

  • 70 Questions
  • 44 Answers
  • 7 Best Answers
  • 577 Points
View Profile
Gopal Mishra

I want to know minimum time required for finishing activities because I want to schedule a residential project in msproject

 

  • 0
  • 5 5 Answers
  • 4,020 Views
  • 0 Followers
  • 3
  • Share
    Share
    • Share on Facebook
    • Share on Twitter
    • Share on LinkedIn
    • Share on WhatsApp

5 Answers

  • Voted
  • Oldest
  • Recent
  1. AdityaBhandakkar

    AdityaBhandakkar

    • 11 Questions
    • 250 Answers
    • 2 Best Answers
    • 0 Points
    View Profile
    AdityaBhandakkar User
    2020-08-02T09:29:48+05:30Added an answer on August 2, 2020 at 9:29 am
    Minimum time required to complete activities in residential building construction?

    It depends on the length and complexity of the project.

    Time of project varies from project to project. But, If tasks are scheduled properly and interrelated, all works. Then you did it in minimum time.

    More time is required for analysis and finishing, so it must be done optimistically.

    The economy is very important to point during project scheduling. Because of the increase in time, decrease the economy of the project.

    • 37
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  2. aviratdhodare

    aviratdhodare

    • 37 Questions
    • 252 Answers
    • 0 Best Answers
    • 480 Points
    View Profile
    aviratdhodare
    2020-09-18T18:36:44+05:30Added an answer on September 18, 2020 at 6:36 pm

    If you require a nice standard building with good amount of curing and strength, it will easily take 6–9months for completion. Sometime it would even take 12months depending on the area of construction, availablity of labour and in cases of pandemics(like in the case of corona now).

    Also the completion time depends of how you make the payment. If you depend on bank loan then there are chances of the work getting a bit prolonged as bank disburse s the amount at different stages of completion.

    Always keep a month as buffer period after the agreement is done as the contractor will have to get the site ready, install all the required facilities like electricity, bore, watchman, getting structure drawing cross verifying them, soil testing, etc.

    Work upto the first slab usually takes time as there would be a lot of ground work to be done, there after the work can be done faster and simultaneous works can be done.

    Just make sure you talk and discuss the time limit with your contractor clearly and mention it in the agreement so both the parties have enough clarity about this. Also once the building is nearing its final stages do not pressure the contractor to complete soon otherwise there might be chances of the work getting affected.

    • 34
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  3. aviratdhodare

    aviratdhodare

    • 37 Questions
    • 252 Answers
    • 0 Best Answers
    • 480 Points
    View Profile
    aviratdhodare
    2020-09-18T18:35:38+05:30Added an answer on September 18, 2020 at 6:35 pm

    If you require a nice standard building with good amount of curing and strength, it will easily take 6–9 months for completion. Sometime it would even take 12months depending on the area of construction, availablity of labour & in cases of pandemic (like in the case of corona now).

    Also the completion time depends of how you make the payment. If you depend on bank loan then there are chances of the work getting a bit prolonged as bank disburse s the amount at different stages of completion.

    Always keep a month as buffer period after the agreement is done as the contractor will have to get the site ready, install all the required facilities like electricity, bore, watchman, getting structure drawing cross verifying them, soil testing, etc.

    Work upto the first slab usually takes time as there would be a lot of ground work to be done, thereafter the work can be done faster and simultaneous works can be done.

    Just make sure you talk and discuss the time limit with your contractor clearly and mention it in the agreement so both the parties have enough clarity about this. Also once the building is nearing its final stages do not pressure the contractor to complete soon otherwise there might be chances of the work getting affected.

    • 33
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  4. Komal Bhandakkar

    Komal Bhandakkar

    • 46 Questions
    • 255 Answers
    • 0 Best Answers
    • 2,040 Points
    View Profile
    Komal Bhandakkar AUTHOR
    2020-10-05T20:57:53+05:30Added an answer on October 5, 2020 at 8:57 pm
    This answer was edited.

    The most average time to build a multi family house which varies the number of units in a building.

    In 2014 building the twenty or more units took near about 15 months to complete from the time of obtaining permits. And properties with 10 to 19 units physically finished in 13.6 months whereas 5 to 9 unit building came in at  11.5 months.

    The average time from permits to start does not follow the same pattern with respect to property size. Properties with 10 to 19 units had the longest average waiting period.


     

    • 28
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  5. ABDULLAHHNAQVI
    2018-01-10T06:13:56+05:30Added an answer on January 10, 2018 at 6:13 am

    it depends on many factors but basically on its size and type of finishing required so plz specify and exact time can be optimized

    • 0
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp

You must login to add an answer.

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Need An Account, Join Here

Sidebar

Popular Articles

  • Gopal Mishra

    Types of Foundation for Buildings and their Uses [PDF]

  • Gopal Mishra

    Compressive Strength of Concrete -Cube Test [PDF], Procedure, Results

  • Padmanabhan G

    Methods of Rainwater Harvesting [PDF]: Components, Transport, and Storage

  • Sadanandam Anupoju

    16 Types of Heavy Equipment Used in Construction

  • Fasi Ur Rahman

    Standard Size of Rooms in Residential Building and their Locations

Recent Articles

  • Xian

    Bricklaying Robots in Construction #2

  • Xian

    Welcome to the Gutenberg Editor

  • Xian

    Bricklaying Robots in Construction

  • Ravi Panwar

    Rongjiang Bridge: The World’s Longest Bridge of Rigid Girder and Flexible Arch

  • Ravi Panwar

    Qinghai–Tibet Railway: The Longest and Highest Highland Railway in the World

Recent Questions

  • Shailendra

    In what case is a Shear Key provided in Foundation?

    • 0 Answers
  • Salman

    What is piping technology for termite treatment in building?

    • 0 Answers
  • nikeetasharma

    Which instrument is widely used for surveying?

    • 1 Answer
  • nikeetasharma

    Which type of reinforcement are used in pre-stressing?

    • 0 Answers
  • Bhavani Pesaru

    How can we use magnetic levitation method in civil engineering?

    • 0 Answers

Explore

  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Footer

  • Home
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
  • Ask Questions
  • Write for us
  • Popular Questions
  • Facebook
  • Instagram
  • Telegram

© 2009-2021 The Constructor. All Rights Reserved.