Join

Join TheConstructor to ask questions, answer questions, write articles, and connect with other people. When you join you get additional benefits.

Have an account? Log in
Continue with Facebook
Continue with Google
or use


Have an account? Log in Now

Log in

Log in to TheConstructor to ask questions, answer people’s questions, write articles & connect with other people. When you join you get additional benefits.

Join Here

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Log in Now

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Don't have account, Join Here
Become VIP Member
The Constructor Logo The Constructor Logo
Log inJoin

The Constructor

The Constructor Navigation

  • Articles
    • Recent Articles
    • Popular Articles
    • Write Article
  • Questions
    • Recent Questions
    • Popular Questions
    • Polls
    • Ask a Question
  • Categories
    • How To Guide
      • Material Testing Guide
    • Concrete
    • Building
      • Brick Masonry
      • Building Materials
      • Building Tips
    • Construction
      • Equipments
      • Management
    • Digital tools
    • Geotechnical
      • Foundation
Search
VIP Dashboard

Mobile menu

Close
Ask a Question
  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

What is the difference between Tender and Contract Documents?

Home/ Questions/Q 11626
Next
Closed

Do you need to remove the ads? Become VIP Member

Asked: May 31, 20162016-05-31T14:20:24+05:30 2016-05-31T14:20:24+05:30In: Construction
Gopal Mishra
Gopal Mishra

Gopal Mishra

  • 70 Questions
  • 44 Answers
  • 7 Best Answers
  • 577 Points
View Profile
Gopal Mishra

What are the difference between Tender and Contract Documents?

Can we mention tender documents as contract document while issuing LOA to  the Contractor. if no then what is the difference?

  • 26
  • 13 13 Answers
  • 44,484 Views
  • 3 Followers
  • 14
  • Share
    Share
    • Share on Facebook
    • Share on Twitter
    • Share on LinkedIn
    • Share on WhatsApp

13 Answers

  • Voted
  • Oldest
  • Recent
  1. Gopal Mishra

    Gopal Mishra

    • 70 Questions
    • 44 Answers
    • 7 Best Answers
    • 577 Points
    View Profile
    Best Answer
    Gopal Mishra
    2016-06-01T23:45:13+05:30Added an answer on June 1, 2016 at 11:45 pm

    To understand the difference between tender documents and contract documents, first we have to understand what these documents contain.

    Tender Documents:

    A tender is an offer in writing to contractors to execute the some specified works or to supply specified materials within a fixed time frame and as per conditions of contract and agreement between the contractor and the owner or the department or the party.

    The tender documents contains the bill of quantities (BOQ), specifications of the works to be carried out, time frame for the completion of the work, conditions of the contract and plans and drawings. These documents are provided to the contractor on the payment of certain fees. The contractor who quotes the lowest rates for the overall works are offer the contract to execute the work.

    Contract Documents:

    Contract documents are the agreement between the owner or the party or the department and the contractor to execute the works as specified in the tender documents as per conditions of contract on the rates quoted by the contractor.

    The difference between Tender and Contract Documents:

    The difference here to be noted is that tender documents are offered to as many contractors as possible to get the lowest quotes for the work specified, while the contract documents are signed only with the contractor with lowest tender or rates.

    While the tender documents contains the conditions of contract and all the details for the specified work, there is not much difference between the two in terms of contents. But tender documents can not be submitted as Letter of Acceptance (LOA) as these are two different types of documents. While a tender document can not bind the contractor to do the work, a contract document binds the contractor to complete the work as per the agreement.

    Simple Example to understand the difference between tender and contract documents:

    When you are selected for a job in a company you are offered offer letter to join the company. But getting selected in a company does not mean that you join the same company, you may have other offer letters as well. But when you sign the letter of acceptance (LOA) for the job, you are bound to join the company. So, here offer letter from the company is a tender document and LOA is the contract document.

    • 50
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  2. ikhlaq
    2016-06-02T13:42:35+05:30Added an answer on June 2, 2016 at 1:42 pm

    Thank you Gopal for your clarification. The final price of the contractor is based on tender documents hence can we include tender document in LOA if not then why. Also the documents that were provided to contractor during tender stage can the same documents be mentioned as  as contract document in LOA.

    • 1
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  3. Gopal Mishra

    Gopal Mishra

    • 70 Questions
    • 44 Answers
    • 7 Best Answers
    • 577 Points
    View Profile
    Gopal Mishra
    2016-06-02T14:19:29+05:30Added an answer on June 2, 2016 at 2:19 pm

    Hi ikhlaq,

    In a tendering process, the prices are submitted by the contractors in a sealed tender. The contractor with lowest price called as L1 and others L2, L3 for next higher rates.

    The next step after decalring L1, L2 and L3 is call them for negotiation for further reducing the rates. If a contractor with L2 or L3 reduces rates below L1, L2 or L3 can also be offered the contract.

    Thus, the rates quoted by contractors in a tender document is not final and can change during the negotiation stage. Thus, the tender document can not be included in the contract document. After the negotiation is completed, the LOA is signed between the L1 and the owner / party and the contractor to accept the terms and conditions and the rates quoted.

    The LOA documents contain all the documents in tender documents as well as revised rates quoted by the contractor. But the tender documents are not the acceptance of the contractor do complete the work as per conditions mentioned in it. But when a contract document i.e. LOA is agreed and signed by both parties, the contractor has to complete the work as specified and as per the terms and conditions in the document.

    The point here is to understand that the tender and contract documents may not have much difference in their contents, but they differ by their title, their importance and their legal validity. So, tender documents can not be issued as LOA.

    • 1
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  4. Hassan Colley
    2016-06-21T02:38:31+05:30Added an answer on June 21, 2016 at 2:38 am

    Basically, tender documents and contract documents refers to the same set of documents. But the major distinction is that the former is the appropriate title for the document before signing the contract and it is being used to select a suitable contractor to execute the works.  While the latter is the appropriate title for the documents after signing the contract and it is used to execute the works. In other words, before the awarding the contract, the set of documents issued are called tender documents and after award of the contract the documents issued becomes contract documents. If you agree with me, indicate and if you differ, let’s have your opinion. Thank you.

    • 14
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  5. veronicajan
    2016-06-23T00:43:08+05:30Added an answer on June 23, 2016 at 12:43 am

    Thanks guys for all these awesome explaination its very useful.thanks.

    • 1
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  6. Pa Alieu Jagne
    2016-06-25T20:20:14+05:30Added an answer on June 25, 2016 at 8:20 pm

    Mr Gopal mishra, is award of contract only limited to the bidder with the lowest rates? I think it is based on best financial and technical offer. Am i right?

    • 0
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  7. Lokesh Sharma
    2016-07-24T22:55:36+05:30Added an answer on July 24, 2016 at 10:55 pm

    Hii
    Gopal
    Thanks for clarification about tender and contract documents with good example

    • 1
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  8. rakesh gupta
    2016-08-29T22:45:38+05:30Added an answer on August 29, 2016 at 10:45 pm

    What proucture can be adopted while preparing tender inviting docucments by an artitect

    • 0
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  9. Enigneers Chaupal
    2016-09-12T04:28:06+05:30Added an answer on September 12, 2016 at 4:28 am

    This article is quite useful for knowing more about tender and contract documents. Thanks so much!

    • 2
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  10. Jinish Patel
    2016-09-30T02:38:08+05:30Added an answer on September 30, 2016 at 2:38 am

    Tender is one type of invitation and contract is invitation card. Tender is invited in ppp model or when government have not sufficient  money and man power at that time government or any agency is publish or open a tender and for taking that work  different contractors submit their own rates to government or agency and whom of have  lower price rate, that contractor have going that tender and that contractor can work on that tender but for to do work some conditions have signed to contractors and that conditions like you have to finished work in specific time period, specific qualities, and money despotism like EMD, SD, etc etc and these conditions are the  contract documents.

    • 5
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  11. MUbeen
    2016-10-05T01:18:17+05:30Added an answer on October 5, 2016 at 1:18 am

    Gopal Mishra excellent Example Thanx.

    • 1
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  12. Abdul-majid Mussa
    2016-10-08T23:58:39+05:30Added an answer on October 8, 2016 at 11:58 pm

    Tender document is offer from the client to contractor to permanent work

    Contract document is agreement from department or client or organization to the contractor for perform work

    • 4
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
  13. M-KUBE QS & CONTRACTORS
    2016-12-08T09:45:42+05:30Added an answer on December 8, 2016 at 9:45 am

    Tender Document:

    It is a Pre-Bidding document. This document mainly describes about four matters, they are 1.Eligibility criteria of the contractor, 2. Time line of the project 3. Working Procedure of the contract and 4. Specification of materials with quantities(BOQ).

    There are also some restrictions to get tender documents. In some cases, The contractor who is eligible only can get the tender document.

    Bidding:

    Once the rate is quoted by contractor in BOQ, it is sealed in cover and submitted to Tender Inviting Authority Panel. At the date of tender opening , the panel will unsealed the cover and start to name L1, L2 & L3 respectively to the contractor, who quoted lowest value of three members. Then negotiation process will take place, the contractor who comes for the lower price to him the tender will be awarded.

    Eg: At the time of Tender Opening : L1 – 10.25 Cr; L2 – 10.30 Cr; L3 – 10.32

    After negotiation : L1- 10.18 Cr; L2 – 10.23 & L3 – 10.15,

    Now the contract will be awarded to L3

     

    Contract Document:

    It is a Post – Bidding Document. This document is totally of agreement. Once the bidding is over the contractor and client will undergo an agreement that the Project will be completed in scheduled time, with the same specification and  working procedure as mentioned in Tender document. If the project is delayed due to contractor, then the penalty will cover some percent in the total project cost. This agreement is documented as contract Document.

    • 16
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp

You must login to add an answer.

Join for free or log in to continue reading...

Continue with Facebook
Continue with Google
or use


Forgot Password?

Need An Account, Join Here

Sidebar

Popular Articles

  • Gopal Mishra

    Types of Foundation for Buildings and their Uses [PDF]

  • Gopal Mishra

    Compressive Strength of Concrete -Cube Test [PDF], Procedure, Results

  • Padmanabhan G

    Methods of Rainwater Harvesting [PDF]: Components, Transport, and Storage

  • Sadanandam Anupoju

    16 Types of Heavy Equipment Used in Construction

  • Fasi Ur Rahman

    Standard Size of Rooms in Residential Building and their Locations

Recent Articles

  • Xian

    Bricklaying Robots in Construction #2

  • Xian

    Welcome to the Gutenberg Editor

  • Xian

    Bricklaying Robots in Construction

  • Ravi Panwar

    Rongjiang Bridge: The World’s Longest Bridge of Rigid Girder and Flexible Arch

  • Ravi Panwar

    Qinghai–Tibet Railway: The Longest and Highest Highland Railway in the World

Recent Questions

  • Shailendra

    In what case is a Shear Key provided in Foundation?

    • 0 Answers
  • Salman

    What is piping technology for termite treatment in building?

    • 0 Answers
  • nikeetasharma

    Which instrument is widely used for surveying?

    • 1 Answer
  • nikeetasharma

    Which type of reinforcement are used in pre-stressing?

    • 0 Answers
  • Bhavani Pesaru

    How can we use magnetic levitation method in civil engineering?

    • 0 Answers

Explore

  • Questions
    • Popular Questions
    • Trending Questions
    • New Questions
    • No Answer Questions
  • Ask Questions
  • Write for us
  • Building
    • Brick Masonry
    • Building Materials
    • Building Tips
    • Formwork/Shuttering
  • Concrete
    • Concrete Admixtures
    • Cement
    • Concrete Cracks
    • Concrete Properties
  • Construction
    • Construction Equipments
    • Construction Management
    • Construction Project
    • Estimating & Costing
  • How To Guide
    • Material Estimation
    • Repair/Protection Guide
    • Material Testing Guide
    • Mix Design Guide
    • Rate Analysis
  • Geotechnical
    • Foundation Engineering
    • Ground Improvement
  • Structural Engineering
    • Strengthening of Structure
    • Structual Inspection
    • Structural Detailing
  • Surveying
  • Tips

Footer

  • Home
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
  • Ask Questions
  • Write for us
  • Popular Questions
  • Facebook
  • Instagram
  • Telegram

© 2009-2021 The Constructor. All Rights Reserved.