In construction project, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: 1.subsequent tasks ("free float"). 2.project completion date ("total float").
In construction project, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:
1.subsequent tasks (“free float”).
2.project completion date (“total float”).
nikeetasharma
CBR test is done in construction materials laboratories to evaluate the strength of soil subgrades and base course materials. The purpose of soil sample soaked in water for 7days is to find out the strength of the sample after soaking continuously in water. The effective CBR should be 75% .
CBR test is done in construction materials laboratories to evaluate the strength of soil subgrades and base course materials.
The purpose of soil sample soaked in water for 7days is to find out the strength of the sample after soaking continuously in water. The effective CBR should be 75% .
See less